Two custom shopping bag orders of identical size and quantity can ship three weeks apart, and the difference is almost never how fast the factory runs. It is decided before production starts — by how quickly artwork is approved, whether the fabric was in stock, and how many colours had to be screened.
This page sets out the six stages that actually consume calendar time between a purchase order and a delivered carton, marks which stage sits on your side of the table, and shows how to check that a quoted lead time is a schedule rather than a number someone guessed. For reference, our own figures are about seven days for a development sample and about 30 days for a 5,000-piece run.
Production is the one stage a factory controls almost completely, and it is rarely the stage that slips. The stages that slip are the handoffs: an artwork revision, a second sample round, a fabric that had to be dyed, a colour added after screens were cut.
Each stage below only opens when the one before it closes. That is why the useful question is never "what is your lead time" in isolation, but "which stages does that number include, and what happens to it if this one reopens".
The clock starts on the day artwork is approved, not the day the order is placed. A complete file means vector artwork with text converted to outlines, Pantone references rather than screen colours, and the print area marked on a dieline that shows every panel — including whether the gussets carry print.
This stage is on your side. It is also the stage where most schedules quietly die, because approval is often split across a marketing owner, a brand owner and a purchasing owner, and each one reviews it separately. Our guide to confirming artwork before production lists the checks that catch most of these before the file is released.
It is worth being blunt about this stage, because it is the one buyers most often treat as free. Artwork confirmation is a duration of its own, not an instant: it sits in front of the seven-day sample rather than inside it, so a file that takes ten days to settle has already consumed more calendar than the sampling it delays.
A sample proves four things: how the material feels, whether the colour matches, how the bag is constructed, and where the print lands. It does not prove how registration holds across a full run, whether the running shade drifts, or how the handle behaves after a thousand uses.
On our own line a development sample takes about seven days to make. That figure is the sample itself, not the courier carrying it to your desk, and it assumes the artwork was approved before the sample started — a sample made against unfinished artwork is being built to a specification that does not exist yet.
The scheduling consequence is simple. Every additional sample round costs a full sample cycle plus the transit time in both directions, and a round that crosses a border costs it twice. Decide before the first sample what would make you reject it — because deciding after it arrives is how a two-round programme becomes a four-round one.
This is the stage buyers most often underestimate. Standard white or black non-woven in a common weight is usually stock, and the stage is short. The following are not stock, and each one adds a manufacturing step ahead of your bags:
Fabric dyed to a specific Pantone reference rather than a stocked colour
Laminated stock, where the film and the base have to be married before printing
A non-standard film thickness on a PVC or clear bag
Certified recycled fibre, where the transaction certificate has to be issued for the shipment as well as the goods produced
The recycled case is worth flagging separately. Certified rPET is not just a material choice, it is a documentation chain, and the certificate that covers your order is issued per shipment — so it has its own place in the schedule. The rPET guide covers what to ask for and when.
Silkscreen needs one screen per colour, cut before the run. Gravure needs engraved cylinders, which take the longest to prepare and pay back only at volume. Heat transfer needs a printed carrier film. Digital needs no setup at all.
Setup is the reason a colour change late in the process is expensive in time as well as money. A design that moves from four colours to five after approval does not add one screen — it reopens the gate that was already closed.
For reference, a 5,000-piece run on our line takes about 30 days from approved pre-production sample to packed cartons. That figure assumes the material is booked and the print colours are frozen. Add a colour after the screens are cut, switch to a fabric that has to be dyed to match, or change the quantity, and the number moves — which is why it is quoted per order rather than published as a promise.
The run opens when the pre-production sample is approved, not when the order is confirmed. If your programme requires a third-party inspection, book the inspector before the run ends: an inspection slot requested after the goods are packed adds days that were never in the production plan. What we check at each point is set out on our quality control page.
This is the stage that makes two quotes incomparable without anyone lying. A lead time of the same number of days can mean four different dates depending on the shipping term:
EXW — the clock stops when the goods leave the factory floor
FOB — it stops when the container is loaded at the port of departure
CIF — it stops when the goods arrive at the destination port, before clearance
DDP — it stops when the goods are delivered to your door, duty paid
Ocean transit and customs clearance sit between the middle two, and neither is controlled by the factory. If your in-hands date is fixed, the only term that answers your question directly is DDP, because it is the only one that includes everything after the container.
Stage | What opens it | Where it slips | Whose side |
|---|---|---|---|
Artwork and dieline | Approved vector file with Pantone references | Revisions after release; approval split across several people | Buyer |
Sampling | Factory receiving the approved file | Extra rounds; sample transit between countries | Shared |
Material booking | Confirmed weight, colour and film thickness | Dyed-to-match fabric; laminated or special film; certified fibre paperwork | Split |
Print setup | Final colour count and frozen artwork | Colours added after screens or cylinders are made | Buyer |
Production and inspection | Pre-production sample approved | Inspection slot booked too late; material arriving late | Split |
Packing and handover | Final inspection passed | Carton marks or documents reissued; term quoted being EXW or FOB when you assumed door delivery | Shared |
Counting forward from the order date tells you when the factory thinks it can ship. Counting backwards from the date you need the bags tells you whether the order is possible at all. The order is always the same:
Start with the date the bags must be in hand
Subtract delivery transit from the named port or door, including clearance
Subtract the inspection window and the packing days
Subtract the production run
Subtract each sample round and the transit in both directions
Subtract the time you will realistically need to approve artwork
Run the arithmetic with our own figures and the shape becomes clear. Seven days of sampling plus 30 days of production is 37 days before a single day of transit is counted — so an order that still needs a sample cannot be in hand in four weeks. Four weeks is not impossible, but it is a conditional case rather than a normal one. It works when the material is already sufficient and on the floor, when the artwork is already confirmed and frozen, when no new sample round is required, and when the shipment is booked before the run ends; then 30 days of production plus packing and loading is the whole schedule. Where the material still has to be dyed or laminated, or the artwork still has to be agreed, both are durations in their own right — and the four-week case disappears. Same bags, same factory; the difference is entirely in what was already done before the countdown started.
Part of the schedule | Figure on our line | What that figure assumes |
|---|---|---|
Development sample | About 7 days | Artwork approved before the sample starts; courier time to your desk is not included |
Production, 5,000 pieces | About 30 days | Material booked, colour count frozen, pre-production sample already approved |
Ready to ship in 4 weeks | Possible, but conditional | Material already sufficient and in stock; artwork confirmed and frozen; no new sample round; shipment booked before the run ends |
Artwork approval, sample transit, inspection, ocean freight | No factory figure exists | Yours or nobody's — count these yourself instead of assuming they are included |
Whatever date is left is the last day you can start. If that date is already in the past, the schedule is not tight, it is impossible at the specification you asked for — and the honest options are to reduce the colour count, move to in-stock material, split the order so part ships by air, or accept a later campaign date. Nothing on that list is a factory problem, which is why it is worth doing the arithmetic before the order rather than after.
What to state | Why it protects the date |
|---|---|
The in-hands date, not the ship date | Every stage is planned backwards from it |
An artwork freeze date | Closes the print setup gate so it cannot reopen |
Material with weight or thickness in figures | Removes the substitution that forces a re-quote mid-schedule |
Colour count and Pantone references | Sets the number of screens or cylinders before the run |
The shipping term and the named port or address | Defines where the quoted lead time stops |
Who books inspection, and by when | An inspection slot is not available on demand |
The document set required with the goods | Certificates and test reports raised after production delay the release |
The RFQ template formats the specification side of this, and the price driver breakdown explains which of these choices also moves the unit cost — because the decision that saves a week sometimes costs a few percent.
Artwork that keeps moving. The single most common cause. Once screens or cylinders exist, every further change reopens a closed gate.
Approval by committee. Three stakeholders reviewing in sequence take three times as long as three reviewing in parallel. Set one internal deadline for comments, not a review chain.
A colour agreed by eye. Approved on a screen or from memory, then disputed against the bulk. Approve against a physical standard on the actual substrate.
Documents raised late. A letter of credit, a certificate requirement or a labelling rule introduced after production has nowhere to go except into the schedule.
Five questions separate a schedule from an optimistic number:
Break the number down by stage. A supplier who can only give one figure is quoting a habit, not a plan.
Ask what it excludes. Sampling is the usual exclusion, and at seven days it only becomes the problem when it has to be repeated.
Ask what happens to the date if one colour is added after approval. The answer tells you whether the print gate is real.
Ask which shipping term the number assumes, and where the clock stops.
Ask for the start and ship dates of the last two orders built to the same specification.
On our own line: about seven days for a development sample, then about 30 days for a 5,000-piece run from the approved pre-production sample to packed cartons. Those 37 days are the part a factory controls. Artwork approval comes before them, and inspection, packing and ocean transit come after them — which is why any supplier who quotes one total figure without asking about your artwork, material and quantity is describing a habit rather than your order. Four weeks is achievable only when the material is already sufficient and the artwork already confirmed; where either still has to be produced, it is not.
It depends which sample. A pre-production sample made from your approved artwork is part of the run and costs little schedule time. A separate development sample, or a second round after revisions, costs a full cycle plus transit each time.
Yes, but only at one of four costs: fewer print colours, in-stock material instead of dyed or laminated stock, a split shipment so part of the order travels by air, or a simpler construction. Asking a factory to compress production without changing any of those usually just moves the risk into quality.
Usually because a repeat is not a rerun. A new dye lot has to match the retained sample, artwork is often re-released and re-approved, and the order joins a different point in the production queue. Confirming a repeat as "same as last time" in writing, with the retained sample referenced, is what keeps the second order as fast as the first.
It changes what the date means. The same production schedule produces four different arrival dates under EXW, FOB, CIF and DDP, because each stops the clock at a different point. Compare quotes on the same term or the comparison is not about price at all.
Often yes, and it is the usual answer when a launch date cannot move. Bags are light for their volume, so the air premium is driven by carton size rather than weight — which makes consolidating cartons worth checking before assuming air freight is unaffordable.